BSBIOS prepares infrastructure on new site to start construction of Omega Green biorefinery in Paraguay

by Erasmo Carlos Battistella

BSBIOS Paraguay, an ECB Gorup company, has started this November 2021 the infrastructure works for the establishment of internal and access roads, as well as all the fencing of the area that will house the Ômega Green project, a mega complex with an estimated investment of US$ 1 billion, which involves the first second generation advanced biofuel plant (HVO and SPK) in the Southern Hemisphere.

A base is also under construction for the installation of the workshop and deposits of the company responsible for preparing the land for the start of construction. The operation of the biorefinery is planned for 2025.

The project update was reported directly to Paraguay’s president, Mario Abdo Benítez, in a meeting held on Monday (15/11). On the occasion, the Minister of Industry and Trade, Luis Alberto Castiglioni, delivered Resolution No. 723 that declares “of Institutional Interest the Omega Green Investment Project”.

The declaration of institutional support by the Paraguayan State to the project reaffirms our partnership with the country and defines Omega Green as of national interest, strengthening its image before international investment agencies. This distinction reflects the importance of an initiative that generates green jobs and GDP.

The document of the Government of Paraguay establishes that the project “will represent a high impact on the national and local economy, since it is a venture that aims at the socio-economic development of the region, the generation of direct and indirect jobs from the construction to the full operation of the project, by enabling productive linkage between agricultural, industrial and service sectors and promoting the use of the energy and natural resources of our country to generate export products with high added value and advanced technology.

Also present at the meeting were the Minister Advisor for Strategic Affairs of the Presidency, Federico González, the President of Itaipu Paraguay, Manuel Maria Caceres, the Counselor of Itaipu, Mrs. Liz Cramer, and the Superintendent of Institutional Relations of the ECB Group, Ricardo Feistauer.

New site is seven times bigger than the previous one

The initial Omega Green project construction work has started on a new 484-hectare site acquired by the company in Villeta, 45 kilometres from Asunción, Paraguay’s capital. The area is 5 kilometres from the previous one, which had 70 hectares, with the advantage of bordering the highway (RuttaVilleta-Alberdi) for 220 meters on one side, and on the other, with a longer stretch of the Paraguay River bank. Another advantage is being located about 100 metres from a power substation (SubestaciónBuey Rodeo).

The land brings us the opportunity to house future expansions, with wider space for the development of the port, as well as allowing us to receive strategic partners who may invest in related activities. The proximity to the paved highway and the power substation also reduces operating costs for the project. The land will have 100 hectares of Permanent Preservation Area (APP), maintaining the identity of the current biome.

With the definitive possession of the land, the change of the area was approved in the Free Zone regime defined by the Government of Paraguay on September 15, 2020 for the Omega Green project, which guarantees the maintenance of the legal conditions of the project for a term of 30 years, renewable for another 30, reinforcing the economic security for the investment.

Launched in February 2019, the Omega Green project is the largest private investment in Paraguay’s history and contemplates the construction of the first advanced biofuels plant in the Southern Hemisphere. It will produce renewable diesel or HVO, an acronym in English for hydrotreated vegetable oil, and renewable aviation paraffin or SPK, fuels that emit fewer greenhouse gases and that will be destined for export to the United States, Canada and members of the European Union.

The entire documentation process for the project has already been concluded, with the registration of the area defined, which guaranteed that the schedule for the beginning of construction work on the project in November of this year will be met.

Related Posts

2 comment

Thais murce 16 de November de 2021 - 19:38

Parabéns ao grupo ECB! Projeto saindo do papel, começando a tomar forma com o início das obras de engenharia. Sonho virando realidade.

Reply
Gino Ewerson Farias 17 de November de 2021 - 10:22

Rezando e torcendo por Omega Green 2 no Brasil, com toda Regulamentação favorável pelo Governo Brasileiro ! Tudo isso me lembra trabalho de formigas no formigueiro e de abelhas na colmeia : Perseverança
!!!

Reply

Leave a Reply to Gino Ewerson Farias Cancel Reply